Construction completed in 2024
Beilsdown Bridge is now open to traffic, with completion of the bridge expected in early 2023.
Bielsdown River Bridge is located at the start of Coramba Road, Dorrigo. Originally constructed in approximately 1950, the timber bridge is ageing and showing signs of deterioration. The new bridge will be a 32.5 m long dual lane concrete structure with a dedicated shared path, which will improve the integrity of the bridge and reduce recurrent maintenance costs into the future. The new bridge is currently being constructed adjacent to the existing timber bridge to ensure community access is maintained. As of August 2022, construction is nearing completion, girders were installed in early August with deck construction works now underway.
Vine Street / Coramba Road, Dorrigo 2453 View Map
Vine Street / Coramba Road , Dorrigo 2453
March, 2022
August, 2022
December, 2022